Critical path method (CPM) and PERT
Ways to find the longest chain of tasks that sets the project’s end date.
Tasks on the critical path have no slack: delaying one delays the whole project. PERT uses optimistic, most likely and pessimistic estimates to handle uncertainty in task durations.
On the exam
To shorten a project, shorten tasks on the critical path. Gantt charts show schedule; CPM shows which tasks drive it.