Timebox management
Fixing the time and resources for a piece of work and adjusting the scope instead.
Each time box has a fixed deadline. If not everything fits, lower-priority features are dropped or deferred rather than extending the deadline. Common in RAD and Agile.
On the exam
In timeboxing, scope flexes; time does not. It helps prevent schedule and cost overruns.
Related terms
- Prototyping and rapid application development (RAD)Building working models quickly so users can react and shape the system.
- Agile developmentBuilding software in short iterations with frequent feedback.
- Scope creepUncontrolled growth in a project’s requirements.