PERT and Gantt charts
Techniques for estimating durations and showing schedules.
PERT estimates each activity from optimistic, most likely and pessimistic times: (O + 4M + P) ÷ 6. Gantt charts show tasks as bars against a timeline, making progress easy to see but dependencies less clear.
On the exam
Three-point estimates → PERT. Bars against time → Gantt. Longest chain of dependent tasks → critical path.
ISACA’s official glossary lists this as: Program Evaluation and Review Technique (PERT). Knowing these names helps you recognise ISACA’s wording in questions.
Related terms
- Critical path method (CPM) and PERTWays to find the longest chain of tasks that sets the project’s end date.
- Work breakdown structure (WBS)The project’s total scope broken down into deliverables and work packages.
- Earned value analysisComparing work done, budget and actual cost to show project health.
CISA Practise CISA questions on this and every other topic, each with all four options explained, in the CISA Question Hub, or take the free CISA diagnostic.
Every CISA term, this one included, is a flashcard in the CISA Flashcard Library.
Test yourself with today’s question of the day.